At our
seminar last week Tom Owen of Keating Chambers discussed the recent Supreme
Court judgment in Cavendish Square Holding BV v El Makdessi and ParkingEye
Ltd v Beavis [2015] UKSC 67 and its implications on liquidated damages
clauses in construction contracts.
The Makdessi
case related to whether clauses agreed in a contract between the parties
were unenforceable penalties. In a construction context, that is a
consideration that always had to be thought through when agreeing the level of
liquidated damages that a contractor would have to pay for failing to complete
a project by an agreed target completion date. If penal in nature (i.e.
more than a genuine pre-estimate of loss) then such clauses would not be
enforceable under the law pre-Makdessi.
In Makdessi
the Supreme Court decided that the law on unenforceable penalties, which
broadly meant that a liquidated damages clause should provide for a payment
that is a genuine pre-estimate of loss, was "an ancient, haphazardly
constructed edifice which has not weathered well.” What was decided in Makdessi
is that the test for an unenforceable penalty should be reformulated.
Considering whether a payment is a genuine pre-estimate of loss is no longer
conclusive. What we must now look at is whether the payment is
“exorbitant or unconscionable” and in considering that in a liquidated damages
context you can look at the employer’s legitimate interest in ensuring that the
target completion date is met.
In theory,
what that will likely mean is that contractors will face a tougher task in
persuading a court that an agreed liquidated damages clause is unenforceable as
the threshold under this new test appears to be higher than that under the old
law. Whether the Supreme Court’s attempt at defining the test gives clarity
will remain to be seen.